Power Outages: Status: Contact: Start Time: End Time:
SSC, 19, 13 Whole Building Outage Proposed J. Willoughby 12/29/2014 07:00 12/29/2014 17:00
Power Outage - LN1, LN2, LN3, LN4 Proposed Paul Powers 12/22/2014 10:00 12/22/2014 12:00
UIM Electrical Upgrade - End Station Unitsub T2 Confirmed Michele Solaroli 12/22/2014 08:00 12/31/2014 12:00
UIM Electrical Upgrade - End Station Loop T6 Secondaries Confirmed Michele Solaroli 12/22/2014 07:00 01/14/2015 17:00
SHMS Clean Power panel Proposed John Riesbeck 12/18/2014 10:00 12/18/2014 15:30
Power Connection for Test Lab Skylight Motorized Shades Completed Josh Caterbone 12/10/2014 05:00 12/10/2014 07:00
Road Closures: Status: Contact: Start Time: End Time:
UIM Cooling Tower Upgrade Confirmed Russell Mattox 01/05/2015 07:00 01/09/2015 17:00
UIM Cooling Tower Upgrade Confirmed Russell Mattox 12/22/2014 07:00 12/26/2014 17:00
UIM Cooling Tower Upgrade Confirmed Russell Mattox 12/18/2014 07:00 12/19/2014 17:00
HVAC Outages: Status: Contact: Start Time: End Time:
Install Valves in Test Lab Basement Chilled Water Piping to Reduce UIM Impact Confirmed Carroll W. Jones 12/30/2014 03:00 12/30/2014 22:00
ARC Governair Monthly Maintenance Confirmed Mike Sprouse 12/11/2014 17:00 12/10/2014 18:00