Power Outages: Status: Contact: Start Time: End Time:
CHL Building Addition Confirmed Rebecca Yasky 01/04/2010 07:00 01/04/2010 17:00
Temp Power tie in at Bldg. 49-E3 Proposed Phil Childress 11/25/2009 07:00 11/25/2009 12:00
test lab north addition Completed rice 11/14/2009 07:00 11/14/2009 03:00
HVAC Outages: Status: Contact: Start Time: End Time:
Bldg. 12 Chilled Water Piping Modification Confirmed Mike Sprouse 11/22/2009 07:00 11/22/2009 19:00
Bldg. 28 Air Handler Maintenance Completed Mike Sprouse 11/17/2009 09:00 11/17/2009 09:30
Bldg. 12 Heat Repairs Completed Mike Sprouse 11/15/2009 06:00 11/15/2009 18:00
Options: