Power Outages: Status: Contact: Start Time: End Time:
CHL Building Addition Proposed Rebecca Yasky 01/04/2010 07:00 01/04/2010 17:00
Temp Power tie in at Bldg. 49-E3 Proposed Phil Childress 11/25/2009 07:00 11/25/2009 12:00
north addition Confirmed rice 10/30/2009 07:00 10/30/2009 08:00
Road Closures: Status: Contact: Start Time: End Time:
SURA Road Closure for South Connector Road Striping Completed Debra Brand 10/29/2009 07:00 10/29/2009 14:00
CEBAF Traffic Circle Completed Debra Brand 10/06/2009 15:17 10/31/2009 17:00
HVAC Outages: Status: Contact: Start Time: End Time:
Bldg. 12 Heat Repairs Proposed Mike Sprouse 11/15/2009 06:00 11/15/2009 18:00
ARC Heat Repairs Completed Mike Sprouse 10/27/2009 16:00 10/30/2009 12:00
VARC Mechanical Room Closure Completed Debra Brand 10/14/2009 07:00 10/28/2009 17:00