Power Outages: Status: Contact: Start Time: End Time:
Test Lab Klystron Area Completed J. Willoughby 08/26/2015 06:00 08/26/2015 07:00
Receptacle hook up Confirmed Josh Caterbone 08/05/2015 06:00 08/05/2015 07:00
Transformer replacement Outage Cancelled Josh Caterbone 07/29/2015 06:00 07/29/2015 06:30
UIM Electrical - End Station Loop Outage Completed Michele Solaroli 07/24/2015 08:30 07/24/2015 09:30
Test Lab Switchboard 2 Completed J. Willoughby 07/21/2015 06:00 07/21/2015 07:00
TEST1 Cancelled jw 07/17/2015 14:59 07/17/2015 14:59
Power Outage - Bldg 98, 99 and BSY Cancelled Caterbone 07/16/2015 07:00 07/16/2015 17:00
Energize test lab High bay receptacles Completed Josh Caterbone 07/15/2015 06:00 07/15/2015 07:00
Bldg 54 and CMSA Power Outage Completed Paul Powers 07/14/2015 06:00 07/14/2015 08:00
UIM Electrical - North Loop Outage Completed Michele Solaroli 07/10/2015 07:00 07/10/2015 08:30
CEBAF F-Wing Outage Completed Jim Yatzeck 06/27/2015 07:00 06/27/2015 15:00
ARC Emergency circuits Confirmed J. Willoughby 06/24/2015 08:30 06/24/2015 09:30
Test Lab Klystron Area 208/120 Completed J. Willoughby 06/23/2015 08:00 06/23/2015 09:00
UIM Elec - North Loop/Hall D Completed Michele Solaroli 06/18/2015 07:30 06/19/2015 17:00
UIM Electrical - North Loop/Hall D Outage Completed Michele Solaroli 06/15/2015 07:30 06/15/2015 11:30
Test Lab FEL-L1 Completed J. Willoughby 06/15/2015 06:00 06/15/2015 15:00
UIM Electrical - North Loop Unitsub E3 Completed Michele Solaroli 06/12/2015 09:00 06/12/2015 10:00
UIM Electrical Upgrade- South Loop/FEL Completed MIchele Solaroli 06/11/2015 07:00 06/12/2015 17:00
T-Trench area power outage Confirmed Josh Caterbone 06/05/2015 07:00 06/05/2015 08:00
LN1 Transformer replacement Proposed Josh Caterbone 06/04/2015 08:00 06/04/2015 16:00
UIM Electrical Upgrade - South Loop/FEL Completed Michele Solaroli 05/29/2015 07:30 05/29/2015 10:00
Test Lab Outage Confirmed J. Willoughby 05/16/2015 07:00 05/16/2015 15:00
provide power to newley installed receptacles Completed Josh Caterbone 04/29/2015 06:00 04/29/2015 07:00
Receptacle hook up for control racks Completed Josh Caterbone 04/28/2015 06:00 04/28/2015 07:00
UIM Electrical - CHL Loop Upgrade Completed Michele Solaroli 04/20/2015 07:00 06/02/2015 17:00
CMSA Power Outage Confirmed Paul Powers 04/08/2015 07:00 04/08/2015 12:00
Power outage for outside golf carts Completed Josh Caterbone 04/08/2015 05:00 04/08/2015 06:00
VTA Power Outage Completed J. Willoughby 04/06/2015 07:00 04/06/2015 08:00
UIM Electrical Distribution - North Loop Completed MIchele Solaroli 04/01/2015 08:00 04/02/2015 17:00
Bldg. #97, 2nd Fl - Electrical Breaker Replacement Completed Maynard Brown, III 03/30/2015 07:00 03/30/2015 08:00
Install proper size ground wire for outlets Completed Josh Caterbone 03/20/2015 05:00 03/20/2015 07:00
3rd floor power outage for the ARC Completed Josh Caterbone 03/07/2015 07:00 03/07/2015 12:00
Road Closures: Status: Contact: Start Time: End Time:
Road Outage - Bohr Blvd. North at Building 89 (ATS) Confirmed Andrew Crumbly 09/02/2015 07:00 09/02/2015 17:00
Cebaf Parking Lot Confirmed acrumbly@jlab.org 09/01/2015 08:00 09/01/2015 10:00
Sills at Entrances to Truck Ramps for Hall A & B Completed Suresh Chandra 08/17/2015 08:00 10/01/2015 17:00
CEBAF Center F Wing Roof Recoating Confirmed Ed Winslow 07/29/2015 07:00 07/30/2015 18:00
UIM Communication - Road Work Between Bldg 89 and North Linac Confirmed Michele Solaroli 07/28/2015 08:00 07/28/2015 13:00
Test Holes at NE Corner of Test Lab Completed Ed Winslow 07/24/2015 07:00 07/24/2015 18:00
Manhole delivery Confirmed Paul Elliott 07/01/2015 07:00 07/01/2015 09:00
Road Closure - CEBAF Blvd (North Access Bldg), Bohr Blvd South (West Arc) Completed Russell Mattox 05/27/2015 08:00 05/27/2015 16:00
RadCon ditch cleanout Completed winslow 04/14/2015 07:00 04/17/2015 17:00
Concrete Walkway Slabs Replacement at VARC & ARC Confirmed Suresh Chandra 03/12/2015 08:00 03/16/2015 17:00
HVAC Outages: Status: Contact: Start Time: End Time:
Bldg 28 SSC 28-AHU-1 Maintenance Completed Mike Sprouse 07/17/2015 07:00 07/17/2015 08:00
ARC Governair Unit Outage Confirmed Todd Meier 07/10/2015 06:30 07/10/2015 07:30
Bldg 12 A-Wing HVAC Repair Completed Mike Sprouse 06/19/2015 06:00 06/19/2015 10:00
Bldg. 12 C-Wing HVAC Repairs Completed Mike Sprouse 06/14/2015 06:00 06/14/2015 19:00
Switchover to CUP Chiller Completed Carroll W. Jones/Mike Sprouse 05/15/2015 11:00 05/14/2015 12:00
Bldg 12 C-Wing HVAC Fan Balancing Completed Mike Sprouse 05/06/2015 08:45 05/06/2015 12:00
ARC GovernAir Failure Completed Mike Sprouse 04/16/2015 09:55 04/16/2015 13:00
Water Outages: Status: Contact: Start Time: End Time:
F-Wing CEBAF Parital Domestic water Interruption Confirmed acrumbly@jlab.org 09/01/2015 16:00 09/01/2015 19:00
TED Domestic Water Leak Repair Completed Mike Sprouse 04/01/2015 20:00 04/01/2015 21:00
Gas Outages: Status: Contact: Start Time: End Time:
Building 60 (CUP) Natural Gas Outage Proposed Jim Yatzeck 07/20/2015 09:00 07/20/2015 13:00
Control System Outages: Status: Contact: Start Time: End Time:
Switchover to ARC Building New JCI Frontend HVAC Control System Controllers Confirmed Carroll W. Jones 07/28/2015 13:00 08/07/2015 17:00
Installation of Replacement ARC JCI Control System Frontend Controllers Completed Carroll W. Jones 07/08/2015 07:00 07/08/2015 08:30
General Outages: Status: Contact: Start Time: End Time:
Moving Concrete Blocks from CMAS Completed Suresh Chandra 09/01/2015 13:36 09/02/2015 17:00