Power Outages: Status: Contact: Start Time: End Time:
UIM Electrical Distribution - End Station Loop - T1 Proposed Michele Solaroli 10/06/2014 07:00 10/17/2014 17:00
TED 2nd Floor AP-2-2 Proposed J. Willoughby 10/02/2014 06:00 10/02/2014 08:00
UIM Electrical Distribution - End Station Clean Power Cancelled Michele Solaroli 09/22/2014 07:00 09/26/2014 17:00
UIM Electrical Distribution Upgrade - End Station Loop - T10 Completed Michele Solaroli 09/22/2014 07:00 09/25/2014 17:00
UIM Electrical Distribution - End Station Loop Completed Michele Solaroli 09/08/2014 12:00 09/24/2014 17:00
Road Closures: Status: Contact: Start Time: End Time:
S. Bohr Blvd Road Closure - Shipping Container Relocations Completed David Fazenbaker 09/26/2014 07:00 09/26/2014 12:00
Paving on North of CEBAF Center Completed Suresh Chandra 09/26/2014 01:00 09/29/2014 12:00
HVAC Outages: Status: Contact: Start Time: End Time:
ARC Lab Governair Unit Final Condenser Fan Controller Repair Confirmed Carroll W. Jones 09/26/2014 16:00 09/26/2014 18:00
Control System Outages: Status: Contact: Start Time: End Time:
Installation of Hot UPW Boiler Control Interface Cards Confirmed Carroll W. Jones 09/24/2014 13:00 09/25/2014 17:00