Power Outages: Status: Contact: Start Time: End Time:
DP-HVAC-M-1 Confirmed J. Willoughby 06/18/2013 06:00 06/18/2013 07:00
panel AP-HVAC-M-1 Cancelled rice 06/07/2013 06:00 06/07/2013 08:00
South Test Lab Outage Completed FM 06/01/2012 07:30 06/01/2014 00:00
Road Closures: Status: Contact: Start Time: End Time:
North parking lot of test lab Proposed Ken Mitchell 06/24/2013 06:00 06/28/2013 17:00
HVAC Outages: Status: Contact: Start Time: End Time:
Replace American Automatrix Sage Controller with Two Honeywell JACE Controllers Confirmed Carroll W. Jones 06/17/2013 00:27 06/17/2013 00:27
Troubleshoot Test Lab TLA Phoenix System Communication & Exhaust Airflow Mod Completed Carroll W. Jones 06/13/2013 15:00 06/13/2013 17:00
Bldg 12 B-Wing AC Maintenance Confirmed Mike Sprouse 06/05/2013 07:00 06/05/2013 09:00
Water Outages: Status: Contact: Start Time: End Time:
ARC/CEBAF Domestic Water Confirmed Debra Brand 06/20/2013 18:00 06/20/2013 19:00
Backflow Device Tesing Confirmed debra brand 06/17/2013 00:00 06/28/2013 00:00
Control System Outages: Status: Contact: Start Time: End Time:
Replace American Automatrix Sage Controller with Honewyell JACE Controllers Confirmed Carroll W. Jones 06/17/2013 10:00 06/21/2013 17:00
Troubleshoot Test Lab TLA Phoenix System Communication & Exhaust Airflow Mod Completed Carroll W. Jones 06/13/2013 15:00 06/13/2013 17:00
Test Outage for New Feature Proposed Walt Akers 06/06/2013 16:53 06/06/2013 16:53