| Scheduled Outage: | |||
| Title: | B01 Power Outage (5-Year extensive PMs) | ||
| Type: | Power Network Telephone Road HVAC Water Gas Controls Other | ||
| Status: | Proposed Confirmed Cancelled Completed | ||
| Proposed by: | Howard Dunlap | E-Mail: | dunlap@jlab.org |
| Start Time: | 10/06/2026 05:00 | End Time: | 10/08/2026 14:00 |
| Description and Impacts: | FMO-E will be conducting extensive 5-year electrical preventive maintenance on electrical panelboards, switchgear, and disconnects throughout Building B.01. These scheduled outages will occur from 10/6/2026 through 10/8/2026. Emergency power will not be affected. Affected systems by date: 10/6/2026: NL-3 SWBD and all associated panels and disconnects, including Building B21 & B.87, which is fed from NL-3 SWBD. 10/7/2026: NL-2 SWBD, NL-4 SWBD, and all associated panels and disconnects, including Building B.07, which is fed from NL-2 SWBD. 10/8/2026: NL-1 SWBD and all associated panels and disconnects, including Buildings B.87. Each day’s work is expected to take approximately 5 to 8 hours to complete preventive maintenance on the electrical equipment. Please see ATLIS-121236 attachments for a summary of dates, panel schedules, and detailed lists of affected systems. | ||
| Affected Areas: | |||
Bldg 01: North LINAC Bldg 07: Exit Stair No. 1 Bldg 21: North Extractor Service Bldg 87: Accelerator Maintenance & Support Bldg 89: Accelerator Technical Support |
|||
| Options: | |||