Scheduled Outage:

Title: North Access Switchboard NA2
Type: Power Network Telephone Road HVAC Water Gas Controls Other
Status: Proposed Confirmed Cancelled Completed
Proposed by: J. Willoughby E-Mail: jasonw@jlab.org
Start Time: 10/14/2019 08:30 End Time: 10/14/2019 10:30
Description and Impacts: UPDATE: OUTAGE MOVED TO 10/14 starting at 8:30AM


Remove power from switchboard NA2 to tie in new sub panel feed. This will remove power from the following:


Building 85 - MCC - will have generator
LCWP-2
LCWP-4

All 120/208 power in B67
All building 480/277 power within the building

Affected Areas:

Bldg 67: North Access
Bldg 85: Machine Control Center


Options: