Scheduled Outage:

Title: Hall B, B91 Beam Dump, & B92 Service Bldg. OUTAGE/PMs
Type: Power Network Telephone Road HVAC Water Gas Controls Other
Status: Proposed Confirmed Cancelled Completed
Proposed by: Howard Dunlap E-Mail: dunlap@jlab.org
Start Time: 12/08/2025 07:00 End Time: 12/12/2025 15:00
Description and Impacts: OUTAGE PLAN FOR NEXT WEEK:

12/8 – 94-MDP-TB – Hall B Truck Ramp (8 hours)



12/9 – 92-SBB1 – B92 and B91 (8 hours)



12/10-12/11 – 92-BCPH1 – Hall B Clean Power (16 hours)



12/12 – 92-SWBD-ESB – Hall B Utility Power (Meter install by subcontractor as well) (8 hours)


*The entire Hall B, B91 Beam Dump, & B92 Service Bldg. will be affected with the exception of emergency power. *


Affected Areas:

Bldg 91: Beam Dump Cooling Building A
Bldg 92: Service Building
Bldg 94: Experimental Hall B