| Scheduled Outage: | |||
| Title: | Hall B, B91 Beam Dump, & B92 Service Bldg. OUTAGE/PMs | ||
| Type: | Power Network Telephone Road HVAC Water Gas Controls Other | ||
| Status: | Proposed Confirmed Cancelled Completed | ||
| Proposed by: | Howard Dunlap | E-Mail: | dunlap@jlab.org |
| Start Time: | 12/08/2025 07:00 | End Time: | 12/12/2025 15:00 |
| Description and Impacts: | OUTAGE PLAN FOR NEXT WEEK: 12/8 – 94-MDP-TB – Hall B Truck Ramp (8 hours) 12/9 – 92-SBB1 – B92 and B91 (8 hours) 12/10-12/11 – 92-BCPH1 – Hall B Clean Power (16 hours) 12/12 – 92-SWBD-ESB – Hall B Utility Power (Meter install by subcontractor as well) (8 hours) *The entire Hall B, B91 Beam Dump, & B92 Service Bldg. will be affected with the exception of emergency power. * | ||
| Affected Areas: | |||
Bldg 91: Beam Dump Cooling Building A Bldg 92: Service Building Bldg 94: Experimental Hall B |
|||