| Scheduled Outage: | |||
| Title: | B12 Shutdown Panels RP1A, RP1E, RP1F RP1H & RP1G | ||
| Type: | Power Network Telephone Road HVAC Water Gas Controls Other | ||
| Status: | Proposed Confirmed Cancelled Completed | ||
| Proposed by: | Howard Dunlap | E-Mail: | dunlap@jlab.org |
| Start Time: | 07/11/2025 05:00 | End Time: | 07/11/2025 07:00 |
| Description and Impacts: | Shutdown Panels RP1A, RP1E, RP1F, RP1H & RP1G to install and terminate breaker for new 3 phase receptacle needed in Computer Center Tech Shop rm. F107. Receptacles throughout the 1st floor F-wing, the Cafe, JCI panel rm. 142, water heater rm. 122B, 12-ACC- 3 & 4 will be affected. CEBAF Computer Center will not be impacted. | ||
| Affected Areas: | |||
Bldg 12: CEBAF Center |
|||