Scheduled Outage:

Title: B19 Facilities Maintenance Shop Power Outage
Type: Power Network Telephone Road HVAC Water Gas Controls Other
Status: Proposed Confirmed Cancelled Completed
Proposed by: Howard Dunlap E-Mail: dunlap@jlab.org
Start Time: 06/24/2025 07:00 End Time: 06/24/2025 03:30
Description and Impacts: Shutdown B19 Facilities Maintenance Shop. Dominion Energy to open overhead power lines to B19, FMO-E to ZVV, and General Facility Maintenance Group to clean gutters. THE ENTIRE BUILDING WILL BE IMPACTED. The outage will take place sometime during normal working hours on Tuesday 06/24/25. Actual start and restoration will be pending Dominion Energy, yet the estimated outage should take roughly 2 hrs.

Affected Areas:

Bldg 19: Facilities Maintenance Shop


Options: